Home » Learning & Resources » Case Studies » PUMPJACK FOUNDATION LIFT
A pumpjack foundation in an active oilfield experienced significant differential settlement, resulting in an out-of-level condition that risked operational efficiency and long-term structural performance.
The structure had settled 5.9 inches on the “T” (heavier) side, creating a major elevation imbalance. The total load on the foundation was extreme—approximately 130,000 lbs from the pumpjack and equipment, plus an additional ~55,000 lbs from the slab, for a combined load near 185,000 lbs.
Several critical challenges defined the project:
A local contractor was engaged to perform the lift using polyurethane injection, with HMI providing technical guidance and support to ensure a controlled and successful outcome under these demanding conditions.
The contractor utilized 4lb/ft3 density structural polyurethane foam in conjunction with an HMI polyurethane system, supported by HMI’s technical expertise in injection strategy and lift control.
Key project specifications:
Injection points were strategically installed around the slab perimeter and beneath critical load-bearing zones, working within confined spaces around the pumpjack structure.
The lift was executed using a staged injection approach, allowing for:
This method ensured that the structure could be raised safely and precisely under extreme loading conditions.
The project was raised back to level within a 1/10th inch tolerance, far exceeding the clients expectations.
Results:
With HMI’s technical guidance, the contractor delivered a high-load, high-precision lift in a constrained, active jobsite environment. The project demonstrates the effectiveness of polyurethane injection for lifting extremely heavy, concentrated loads while maintaining tight tolerances.
It also highlights the importance of proper injection strategy and expert support in achieving reliable results, minimizing downtime, and avoiding disruption to critical operations.
This site is protected by reCAPTCHA and the
Google Privacy Policy and Terms of Services apply.
In 2 days, we will teach you what you need to know to successfully tackle soil improvement projects!
4466 Custer Street
Manitowoc, WI 54220